Construction 1 Schedule

I believe a good schedule is flexible so I highly doubt we will follow this exactly.   However, the following is a brief overview of the year's schedule.

Week 1 (9/1-9/2) Intro. Week

Thursday                   Rules/Syllabus/Intro Activity/One word that comes to mind for Construction/Time Sheets/Hanging file folders/Weekly Bulletin

Friday                        Measurement Activity/Measurement Homework assigned/Sound-Off Box

 

Week 2 (9/6-9/9) Safety Week

Tuesday                    Measurement Homework due/General Safety Video/Lesson/Hand Tools Safety Lesson

Wednesday               Machine Check-off Sheet/General Safety Test/Hand Tools Safety Test/Portable Power Tools Safety Notes/Circular Saw Safety Lesson/Scroll Saw Safety Lesson

Thursday                  Portable Power Tools Test/Circular Saw Hands-on Testing/Scroll Saw Hands-on Testing

Friday                      Hand out tool belts/Begin Saw Horse Project/Test on classmate names/Sound-Off Box/Time Sheets due

 

Week 3 (9/12-9/16) Saw Horse Week

Monday                    Saw Horse Project

Tuesday                    Saw Horse Project

Wednesday              Saw Horse Project

Thursday                    Saw Horse Project

Friday                       Saw Horse Project due/Sound-Off Box

 

Week 4 (9/19-9/23) Job Skills Week

Monday                    Job Applications/Resumes/Resume Information Sheet/

Tuesday                      Resumes in Library

Wednesday               Resumes in Library

Thursday                    Resumes due/How to interview for a job

Friday                       Foreman Interviews/Worker Interviews/Sound-Off Box/Time Sheets due

 

Week 5 (9/26-9/30)

Monday                    Worker Interviews (if necessary)/Layout marking/Floor framing directions/Video on Floor and Wall Framing

Tuesday                      Floor framing

Wednesday               Wall Framing directions/Exterior Frames Windows and doors Video

Thursday                    Wall Framing Diagram

Friday                         Wall Framing/Sound-Off Box

                                 

Week 6 (10/3-10/7)

Monday                    Wall Framing

Tuesday                      Wall Framing

Wednesday               Wall Framing

Thursday                    Wall Framing

Friday                         (Half day) Video on Exterior Sheathing/Sound-Off Box/Time Sheets due

 

Week 7 (10/10-10/14)
Monday                      Wall sheathing

Tuesday                      Wall sheathing

Wednesday               Wall sheathing

Thursday                  Wall sheathing

Friday                         Wall sheathing

 

Week 8 (10/17-10/21)

Monday                      Video on Ceiling and Roof Framing/Roof framing and sheathing

Tuesday                     Install Fascia and Fly rafters/Roof framing

Wednesday               Roof framing

Thursday                    Roof framing

Friday                         Roof framing/Sound-Off Box/Time Sheets due

 

Week 9 (10/24-10/28)

Monday                      Video on roofing and siding finishes/roofing and siding

Tuesday                      Roofing and siding

Wednesday               Roofing and siding

Thursday                    Roofing and siding

Friday                         Roofing and siding

 

Week 10 (10/31-11/4)

Monday                      Pick-up Work

Tuesday                      Pick-up Work

Wednesday               (Half Day) Yard Clean-up Day

Thursday                    Pick-up Work

Friday                         Pick-up Work/Sound-Off Box/Time Sheets due

 

Week 11 (11/7-11-10)

Monday                      Pick-up Work

Tuesday                      Pick-up Work

Wednesday               Pick-up Work

Thursday                    Pick-up Work

 

Week 12 (11/14-11/18)

Monday                      Painting/Trim Work

Tuesday                      Painting/Trim Work

Wednesday               Painting/Trim Work

Thursday                    Painting/Trim Work

Friday                         Painting/Trim Work/Sound-Off Box/Time Sheets due

 

Week 13 (11/21-11/23)

Monday                      Prepare Sheds for Delivery

Tuesday                      Prepare Sheds for Delivery

Wednesday               Yard clean-up (half day)

 

Week 14, 15, 16,17,18 (11/28-12/2), (12/5-12/9), (12/12-12/16), (1/2-1/6), (1/9-1/13)

Monday                      Learning Modules

Tuesday                      Plumbing, electrical, stairs, windows, baseboard, trim, masonry, siding, concrete

Wednesday               Plumbing, electrical, stairs, windows, baseboard, trim, masonry, siding, concrete

Thursday                    Plumbing, electrical, stairs, windows, baseboard, trim, masonry, siding, concrete

Friday                         Plumbing, electrical, stairs, windows, baseboard, trim, masonry, siding, concrete

 

Week 19 (1/17-1/20)

Monday                      Clean-up Yard/Shop Clean-up/Class Evals.

Tuesday                      Review for Final/Shop Clean-up

Wednesday               Final Test/Sound-Off Box